SOFTWARE QUALITY ASSURANCE AUDITS GUIDEBOOK 


NOVEMBER 1990 


PREFACE 

The growth in cost and importance of software to NASA has caused 
NASA to address the improvement of software development across 
the agency. One of the products of this program is a series of 
guidebooks that define a NASA concept of the assurance processes 
that are used in software development . 

The Software Assurance Guidebook, NASA-GB-A2 01 , issued in 
September, 1989, provides an overall picture of the NASA concepts 
and practices in software assurance. Second level guidebooks 
focus on specific activities that fall within the software 
assurance discipline, and provide more detailed information for 
the manager and/or practitioner. 

This is the second level Software Quality Assurance Audits 
Guidebook that describes software quality assurance audits in a 
way that is compatible with practices at NASA Centers. For a 
more generalized view of how software quality assurance audits 
relate to Software Assurance, refer to the Software Assurance 
Guidebook, document number NASA-GB-A201 . 

I . GENERAL 

The NASA Software Assurance Guidebook classifies the software 
quality assurance (SQA) audit as a fundamental quality assurance 
technique. It is the intent of this guidebook to further define 
audits, describe the audit process, and provide a sample 
checklist that can be tailored for use in an audit . The 
guidebook is written for quality assurance practitioners who will 
perform audits, software developers who will be audited, and for 
software project managers and acquirers who have to decide the 
extent of auditing to be done. 



In this guidebook, the term "audit" specifically refers to an SQA 
technique that is used to examine the conformance of a 
development process to procedures and the conformance of products 
to standards . An SQA audit also can examine the conformance of 
the actual status of the development activity to the reported 
status. The term "audit" is used to describe a number of 
additional software activities; however, due to their different 
purpose and focus, they are not addressed in this guidebook. For 
example, the Functional Configuration Audit (FCA) and Physical 
Configuration Audit (PCA) are configuration management (CM) 
activities . Quality (Engineering) Audits and Safety Audits are 
technical activities that evaluate a software product against 
Quality Engineering and Safety requirements . These types of 
audits are not covered in this guidebook. 

II. CONCEPTS AND DEFINITIONS 

An SQA audit is an activity that is performed to determine the 
adherence to, and adequacy of, a project's established software 
development standards and procedures and the effectiveness of 
their implementation. As used in this guidebook, the main 
objective of an SQA audit is to determine the adherence to 
established standards and procedures; checking their adequacy or 
effectiveness is a secondary objective that usually is not 
requested of an auditor. 

In the NASA Software Assurance Guidebook, standards are defined 
as "the established criteria to which software products are 
compared." Software standards include documentation standards, 
design standards, and coding standards. In that guidebook, 
procedures are defined as the "established criteria to which the 
development and control processes are compared." Procedures, 
then, are the step-by-step directions that are to be followed to 
accomplish some development or control process; for example, CM 
or nonconformance reporting and corrective action (NRCA) . In 
other words, standards and procedures are requirements for 
software management, engineering, and assurance; SQA audits 
verify their existence and assess a project's compliance with 
them . 

SQA audits also can compare the actual status of a product with 
reported status . Status auditing is most effective if there are 
objective and consistent criteria for evaluating the level of 
product completeness. For example, Unit Development Folders 
(UDFs) have a cover sheet for recording the progress of a unit 
through its development stages; the folder contains the actual 
product. If a project uses UDFs, then an audit can compare the 
actual product to the cover sheet and to the progress report . 

The actual processes and products examined by an audit will vary 
depending on the objective of the audit. The objective of the 
audit can vary, and is determined by the organization that called 
for the audit . A general audit provides a comprehensive 
overview, while a limited audit might be an examination of 
certain procedures, such as CM, or a check on a certain 
requirement, such as "Are coding standards being followed?" 



An audit may be described as internal or external, depending on 
the organization of origin of the auditor (s) . An internal audit 
is an audit conducted by the SQA staff of the software developer. 
Internal audits are intended to be preventative in nature; to 
detect problems before they become major. 

An external audit is one performed by an independent auditor who 
is outside of the developing organization. External audits are 
most often requested by the acquiring organization, as a means of 
obtaining an independent opinion about the work in progress. 
External audits tend to be more comprehensive in nature than 
internal audits, and usually encompass a broad area of the 
development activity. Such audits usually are requested because 
the acquirer is uncertain of the effectiveness of the internal 
program or because of lack of information and fears about the 
quality of performance on the part of the developer. An 
advantage of an external audit is that the auditor may be more 
objective about a project than an internal auditor; however, an 
external auditor must spend more time learning about the project 
and its development process. 

III. CONDUCTING AN SQA AUDIT 

An SQA audit has four phases: planning and preparation, the site 
visit, reporting, and follow-up. During the planning and 
preparation phase, the auditor gains an understanding of the 
project. Based on the scope of the audit, the auditor determines 
the specific questions that need to be answered, as well as the 
persons to be interviewed and the records and products to be 
examined to answer the questions . The interviews are conducted, 
and records and products are examined during the site visit . The 
reporting phase consists of the exit debriefing of the audited 
project, the preparation of a written report on the audit, and 
clarifying issues and providing related information as needed. 
Follow-up is done by the project, as the problems and 
deficiencies found in the audit are remedied. Follow-up may 
include reauditing to assess the adequacy of the remedies . 

The activities conducted during the phases vary depending on the 
life cycle phase of the project being audited and the scope of 
the audit . The activities also vary depending on whether the 
audit is external or internal; an external audit requires more 
extensive preparation and should examine a more comprehensive 
sample of material than an internal audit . 

Each of the four phases of an audit is described in the following 
sections . The activities of each phase are described as if a 
general, external audit is to be done since this results in the 
greatest detail. Some of the activities may be superfluous to an 
internal SQA audit and may be omitted. 

A. Audit Planning and Preparation 

A general SQA audit should be planned carefully to examine all of 
the software engineering, management, and assurance processes and 
all of their products . Software management processes include 
status reporting and CM. Engineering processes include analysis, 
design, and code. Assurance processes include verification and 



validation (V&V) and NRCA . Products include documents and code. 
If the scope of the audit is more limited, then planning will be 
within the defined limits . A limited audit might examine only 
one of the processes or a limited set of products . Activities 
during the planning and preparation phase are similar for all 
audits, but preparation for a limited audit is focused on the 
identified process or product. 

As a first step, the auditor should understand the objective of 
the software development project and what products are to be 
produced. The auditor needs to know what the contract requires 
in the way of deliverable software and documentation, and what, 
if any, requirements exist for management, engineering, and 
assurance practices. One source of this information may be the 
statement of work and other contract documents . Once it is clear 
what is being developed and what the contract requires, the 
auditor should review management documentation, such as the 
software management, development, and assurance plans to 
understand the processes that will be used to develop and control 
the products . Then the developer' s standards and procedures 
manual should be reviewed to determine the quality standards and 
the detailed procedures planned to be applied to the software and 
the development process. From this background information, the 
auditor should be able to understand the developer' s software 
development process . 

The auditor also should review some recent status reports from 
the developer. These reports will furnish information on the 
stage of completeness of products and may contain information as 
to problem areas . 

After background familiarization and a look at project status, 
the auditor should define the areas that will require the most 
careful and detailed attention, i.e., the processes or products 
that seem to be in some difficulty or whose status is in doubt . 
These areas may be identified by the status reports, discussions 
with the acquirer of the software (if it is the acquirer who has 
requested the audit) , review of nonconformance reports, and the 
results of previous audits . 

Once the auditor understands the project and has identified the 
areas of concentration, he/she should develop a checklist . A 
checklist is a list of items to be examined and questions to be 
asked. Each checklist should be tailored for the specific 
project being audited and its life cycle phase and should reflect 
the scope of the audit . A more comprehensive and less detailed 
checklist is required for a general audit; a limited audit 
requires a checklist that is more detailed in specific areas . 
Guidance on preparing a checklist is given in Chapter VI . A 
checklist is intended to provide the auditor with a "road map" 
during the site visit. It must be complete, so that the auditor 
can know that sufficient information has been gathered if all of 
the checklist items are completed. The checklist questions help 
define the individuals with whom the auditor wishes an interview 
and the types of records that the auditor will examine . 


The auditor should schedule the site visit to the project through 



its assurance staff or other suitable contact after the 
preparation is done and the checklist prepared. During this 
contact with the project, the auditor should specify the intent 
of the audit, the records to be examined, and which people the 
auditor wishes to interview. People to be interviewed will 
include managers, selected developers, CM staff, assurance staff, 
and testers . Copies of the checklist may be furnished to 
increase the project's understanding. The project should be 
prepared to provide the auditor with a convenient working area 
that includes normal office facilities, access to all products 
and records, and interviews with the identified individuals. 

B. The Site Visit 

The purpose of the audit site visit is to collect the data 
necessary to assess that the required products are being 
produced, the degree to which they conform to applicable 
standards, how well procedures are being followed, and that the 
reported status corresponds to the actual status . The audit is 
intended to uncover any significant deviation from standards, 
procedures, or reported status so that corrective action can be 
taken. The auditor uses two basic techniques: interviews with 
project staff and examination of documentation and records. 

The site visit should begin with an entrance briefing, involving 
the auditor and key project staff. During this briefing, the 
auditor should describe the focus of the audit, and identify the 
interviews to be conducted and the records to be examined. The 
entrance briefing may also be used by the project to brief the 
auditor on its processes, key staff members, and current status. 
Time for questions and answers should be included. The auditor 
also should assure the project that an exit interview will be 
held where the auditor will present preliminary findings to the 
project and the project may provide any additional information to 
the auditor. This preliminary exchange of information can 
significantly help to allay the fears of the project and to 
smooth the course of the site visit. 

After the entrance briefing, the auditor should proceed with the 
gathering of information. It is useful to begin the information 
gathering process with interviews, during which the auditor tries 
to understand the realities behind the documented plans and 
procedures . The auditor should learn which individuals carry out 
a procedure, approve a change or fix, keep project records, etc. 
Each individual should be asked to describe his/her perceptions 
of and interactions with the process. The auditor should take 
notes, annotate or develop procedural flow diagrams, ask 
questions to clarify, and make it his/her objective to clearly 
understand the process. In particular, the auditor should be 
alert for indications of shortcuts or abbreviations to the 
procedure. During interviews, the auditor must remember that 
data are being gathered, and that conclusions should wait until 
all of the facts are in. This provides a clearer understanding 
of the actual processes used on the project and eases 
communications with the staff. The checklist developed during 
the preparation phase is used to guide the discussions during the 
interview . 



Once the auditor is sure that the processes and procedures are 
understood as they really exist, he/she should begin examining 
the tangible parts of the project: its products and records. 
Products consist of requirements and design documentation, 
including unit development folders, user manuals, code, etc. 
Records consist of memoranda and forms that document the events 
in the life of a product . They come from CM, NRCA, and V&V, 
among others . 

1 . Records Examination 

The auditor examines records to see if a procedure is being 
correctly followed. Record examination is described below in 
terms of the principal processes that SQA audits examine : CM, 
NRCA, and V&V. Similar activities would be used in the 
examination of other sets of records. 

• CM Audit 

During an audit of CM, the auditor should look at the complete 
change control cycle, beginning with the initial processing of a 
change request; through analysis of impact and dispositioning; 
design, code, and testing; updating of documentation; submission 
of the modified products to the library; and closure of the 
change request . Records to be examined include the change 
requests as processed by the Change Control Board, the work 
authorizing documents issued as a result of approved changes, the 
code and documentation products that are intended to reflect the 
approved changes, and the program library records that capture 
the changes to code and data. Throughout the audit, the auditor 
should be alert for and document any evidence of unauthorized 
changes . 

The records should show the authorization of each change, the 
product (s) to be changed, and the version numbers of the changed 
product. Much of the auditor's attention should be devoted to 
the Program Library or equivalent, since this is where the 
various versions of products and the change documents controlling 
those versions are stored. The auditor should check the products 
in the library to ensure that documentation is up-to-date with 
code changes . The auditor should check the version numbering and 
identification schemes, and the control documents. The records 
should demonstrate that there are adequate security measures in 
place to prevent loss and unauthorized changes . The auditor 
should verify that every item of code and documentation in the 
program library was properly received. 

• NRCA Audit 

When auditing the NRCA system, the auditor should look at the 
complete cycle. The auditor should review the nonconformance 
reports that are filed, to assure that they are completely and 
correctly filled out . The disposition process and board actions 
should be recorded, usually on the same form. The 
nonconformances that result in product changes should be tracked 
to the product, and evidence should be gathered that changes are 



made, tested or reviewed, and approvals for issuance are granted. 
The NRCA procedures will parallel those used in CM, and can be 
audited in much the same way, especially when it comes to the 
program library. In both cases (CM and NRCA), the auditor should 
pay particular attention to corrected products to assure that 
they still satisfy requirements and standards . 

• V&V Audit 

An audit of V&V procedures should include a check of the 
verification matrix or equivalent, to assure that every 
requirement has a test and every test checks a requirement . Test 
plans should be adequate, specifying the test environment, test 
procedures, and the expected results for each test. Test 
procedures should be clear and detailed. Test plans and 
procedures should be reviewed and approved. 

The auditor should verify from SQA records that test procedures 
were followed and that all nonconformances observed during 
testing are recorded in the NRCA system. In addition to testing, 
the auditor should assess other methods of V&V, if used. For 
example, if inspections or another form of peer reviews are used 
to find problems, the auditor should verify that the records of 
the review show that they were done and that corrections and 
changes agreed to in the review are made in the product . 

2 . Product Examination 

The intent of examination of products is two-fold: to see if 
standards are being followed, and to see if status is accurately 
reported. Documents are measured against documentation 
requirements to make sure that all required documents exist, and 
against documentation standards to ensure that they have the 
correct content and style . The auditor must read enough of the 
documents to form an opinion on the above; that is, the auditor 
must be able to determine that a document presented as showing 
the design indeed contains design information. On the other 
hand, the auditor is not responsible for the technical 
correctness of the documents and should not spend time trying to 
ascertain if the documents are correct. 

Code also is examined to determine if it meets standards . Code 
standards are likely to include rules for internal documentation, 
size of modules, styling formats, and other such items that the 
auditor can verify. Rules for coding constructs or variable 
naming conventions are more difficult to verify. If the project 
has a code standards checker, the auditor may run it on some 
code. If the standards checker is to be run at a certain step in 
the development process, or if peer reviews are used to verify 
coding standards, the auditor must have access to those records. 

Products also are examined to compare their status with that 
reported. Documents reported as complete, for example, should 
contain all of the sections given in the table of contents (which 
may be prescribed by a documentation standard) , should be signed 
by the approving authorities, and should contain few, if any, To- 
Be-Determined (TBDs) items. Code implementation usually goes 



through the steps of detailed design, code, peer review, and unit 
test . A module that is reported as complete should have gone 
through all of the above steps, should meet the coding standards, 
and should have whatever approvals are required. The Unit 
Development Folder or equivalent should contain all of the 
evidence to look at status of coding. 

3 . Sampling 

During the process of checking records and products, the auditor 
usually cannot examine each and every item; therefore, some 
sampling process must be used. The auditor must decide on sample 
sizes that can be accommodated in the site visit. The sample 
sizes must be balanced between completeness of coverage (some 
items from each product or set of records) and depth of coverage 
(number of items from a specific product or set of records) . If 
the focus of the audit is limited, the sample size can be larger 
for the specific product or processes that are to be covered. In 
deciding on sample sizes, the auditor must allow time to follow 
up in more depth in areas where the initial sample indicates 
problems . The specific products or records to be included in the 
sample should be chosen by some "randomizing" method, and the 
project staff should not be informed in advance which items will 
be examined and which will not . 

C. Audit Reporting 

Once the interviews and record examination have been completed, 
initial results should be shared with the staff of the audited 
project during an exit interview. The exit interview provides an 
opportunity to clear up misunderstandings and allows project 
staff to present any information that they feel the auditor 
failed to consider. In addition, project staff learn immediately 
about the problems that have been found and can begin making 
plans to correct them. 

After adjusting the initial results to reflect the information 
gathered in the exit interview, the auditor prepares a written 
final report . The report should be organized to highlight the 
most significant results, addressing both problems and 
commendations, and should include a general narrative of the 
audit . An example table of contents for an audit report is shown 
in Appendix A. The audit report should be addressed to the 
management official who arranged for the audit, if the audit is 
external; or directed as required by procedures, if internal. 

The objective of the audit report is to present a clear picture 
of the status of a development activity or a facet of the 
activity to project management. The report must be clear, 
objective, and factual. In some cases, the auditor will find 
that, while procedures are being followed or standards are being 
met, the procedures or standards are not effective in producing a 
quality product . It is the responsibility of the auditor to note 
the specific problems caused by the procedure and/or standard and 
include them in the report. In general, however, problems that 
the auditor identifies should be related to project or 
contractually-required procedures and standards; the auditor's 



opinion of their desirability should not affect his/her 
evaluation of the adherence to them. 

D . Follow-up 

While the auditor' s role is essentially finished after producing 
the audit report, actions to resolve deficiencies identified in 
that report must be taken by project management. Problems that 
are feasible and reasonable to correct should be converted to 
action items and assigned to appropriate individuals . A 
rationale should be developed for those that are not to be 
corrected. It is the responsibility of the developers to improve 
their processes in response to deficiencies identified by the 
audit . The changes should be tracked to ensure they occur and 
are effective and the closure of action items should be 
documented. In many cases, the best way to determine if the 
problems have been solved is through a follow-up audit . 

IV. SQA AUDIT SCHEDULING 

A. Routine Scheduling 

Internal SQA audits should be scheduled frequently enough to 
identify potential problems so that no surprises develop for 
project management. They should be scheduled routinely during 
the life cycle, particularly around life cycle phase transitions. 
The most effective internal audit programs schedule frequent 
audits of small areas of project activity. Frequent auditing, 
combined with other SQA monitoring activities, would assure 
project management that the actual status of the project is 
known, vis-a-vis standards, procedures, and schedules. 

External audits require more planning and interview time, but are 
scheduled much less frequently. The most important time for an 
external SQA audit is at the start of the implementation phase. 
This audit assures that the developer' s standards and procedures 
are implemented in a manner appropriate for the project and that 
they are being followed. A second important time in a project's 
life cycle is the beginning of system integration. An external 
audit helps to assure that the software is ready for integration, 
that test plans and procedures are in place, and that procedures 
for control of the software are not short-circuited. Projects 
that are in trouble or have no internal audit function should 
have more frequent external audits . 

Another factor to consider in the scheduling of audits, either 
internal or external, is the results of previous audits. Each 
SQA audit should include a review of the results and action items 
from any previous audits to confirm closure. If there were a 
number of problems and action items, audits should be scheduled 
more frequently. Projects that follow their procedures, meet 
their standards, and are accurate in reporting schedule and 
status need less frequent auditing. 

B. SQA Audits in Response to Warning Signs 

Some projects may show indications of problems in the development 



process. When warning signs appear, the acquirer should consider 
conducting an external audit as part of its response. The same 
warning signs can be used by the software provider to step up or 
evaluate the effectiveness of its internal audit program. 

The audit program should be intensified if the project exhibits 
any of the following signs : 

• Frequent schedule/milestone changes. 

• Inconsistency of the developer's organizational structure 
with original plans or apparent inconsistency with the structure 
or functionality of the products to be produced. 

• Unexplained fluctuation of project staff level or under- or 
over-staffing compared to estimates. 

• Increases in the number of TBD items and action items 
without adequate progress in solutions. 

• The inability or unwillingness of the developer to provide 
adequate and accurate information on project status, schedules, 
and plans . 

• Continual delay of scheduled software system capabilities to 
later releases/versions. 

• Unreasonable numbers of nonconformances or change requests; 
for example, a large number unresolved, or a sudden increase in 
numbers . An "unreasonable number" might be a suspiciously small 
amount of nonconformances for a complex system. 

There may be other indications that are apparent to project 
management in specific cases. An experienced project manager's 
intuition that something may be wrong is a warning sign that 
should be heeded. An external audit is a cost effective way for 
an acquirer to ascertain the real product status and real 
processes being used by a developer; developer management should 
have an ongoing audit program to assure that no surprises are in 
store for them. 

C. Announcing Audits 

Adequate notification of audits should be provided to the 
developers for a number of reasons. Unannounced (surprise) 
audits are disruptive and demoralizing to the development staff 
and should be avoided. The intent of an audit program should be 
to help promote conformance with standards and procedures and the 
reporting of accurate status, not to "catch in the act" those 
"guilty" of violations . An announced schedule of audits allows 
proper preparation in terms of having required documentation 
available and being prepared to answer the auditor's questions. 

V. SQA AUDITS DURING THE SOFTWARE LIFE CYCLE 

A. Software Concept and Initiation Phase 

During the concept and initiation phase, the software concept is 



developed, the feasibility of the software system is evaluated, 
the acquisition strategy is developed, and, if a contract is to 
be used to acquire the software, procurement is initiated and a 
contract is awarded. Before selecting an organization to perform 
a project, the acquiring organization can request a pre-award SQA 
audit . The intent of this type of audit is slightly different 
from audits performed later in the life cycle. Since there are 
no activities underway on the software that is to be developed, 
the auditor can only review the provider's "corporate" or generic 
standards and procedures, and past projects. If possible, these 
should be examined in the context of the proposed project, so 
that their effectiveness can be judged. This type of audit 
requires an experienced auditor. 

The procedures and standards for the project are formulated 
during this phase . The SQA staff of the acquirer should ensure 
that standards and procedures adopted are appropriate for the 
project and are auditable, i.e., have a clear documentation 
trail, with easy-to-follow steps. They also should make sure 
that the contract allows external audits and requires internal 
audits . 

B. Software Requirements Phase 

During the software requirements phase, the software concept and 
allocated system requirements are analyzed and documented as 
software requirements. Test planning is begun, with a method for 
verifying each requirement identified and included in a 
preliminary test plan. Risks are identified and risk management 
control mechanisms are established. The size and scope of the 
remainder of the project is reevaluated, and changes in resources 
and schedules are made. Methods, standards, and procedures are 
detailed and put in place. The phase ends with a requirements 
review, at which the requirements are agreed to between the 
acquirer and developer and put under CM. 

Internal audits during this phase concentrate on the process of 
developing, documenting, and controlling the requirements . Some 
process should be in place to control the requirements and draft 
documents as they are developed. This process probably will be 
relatively informal, and may include NRCA and an action item 
tracking system. There may be procedures for reporting on 
progress, estimating system and project resources, and risk 
assessment . All of these can be audited to the extent that 
controlled processes are in place. In addition to procedures, 
auditors should verify that requirements documents follow the 
format specified in the documentation standard. 

An external audit, if one is performed during this phase, may 
look at the same items that are covered by an internal audit . In 
addition, an external audit can cover the same items as listed 
for a pre-award audit . 

C. Software Architectural Design Phase 


The objective of the architectural design phase is to develop an 
overall design for the software, allocating all of the 



requirements to software components . The software requirements 
are controlled and managed, and documents baselined following the 
requirements phase are changed only by a formal process . The 
phase ends with the preliminary design review, during which the 
acquirer and developer agree on the architecture of the system 
that is to be produced. Rework and action items resulting from 
the review are tracked and completed. 

Internal and external audits during this phase should include the 
design documentation, verifying that format standards are met. 

The auditor should assure that all requirements are being 
allocated to software components . It is especially important to 
audit the configuration control mechanisms for the requirements 
to make sure that unauthorized and uncontrolled requirement 
change and growth is not occurring. In addition, items such as 
those mentioned in the previous phase, i.e., status reporting, 
action item tracking, and nonconformance reporting should be 
audited . 

D. Software Detailed Design Phase 

During the detailed design phase, the architectural design is 
expanded to the unit level. Interface control documents are 
completed and test plans revised. Constraints and object system 
resource limits are reestimated and analyzed, and staffing and 
test resources are validated. The phase ends with the critical 
design review, and the detailed design is baselined. 

Audits during this phase should focus on the progress and 
documentation of the detailed design. If unit development 
folders (or other similar documentation) are used, they should be 
started during this phase, and can be audited. As auditing is 
done, reported status should be compared with the actual status. 
Any discrepancies should be noted. Both the requirements and the 
architectural design should be under CM and the CM process should 
be audited. Other items listed in the descriptions of the 
previous phases are still applicable. 

E . Software Implementation Phase 

During the implementation phase, the software is coded and unit 
tested. All documentation is produced in quasi-final form, 
including internal code documentation. At the end of the phase, 
all required products should be ready for delivery, subject to 
modification during integration and testing. Audits during this 
phase check the results of design and coding, CM activities and 
program library, NRCA process, and schedule and status of the 
project . 

Internal audits should be frequent during this phase. The 
project staff is usually at its maximum, and there are a great 
number of simultaneous activities. SQA auditing is one of the 
more important ways for management to keep the process under 
control, assure that quality products are being developed, and 
that status is actually as reported. Completed products are 
being sent to test as they are ready, and the products and their 
control process should be audited. Audits should include code 



audits to make sure coding standards are being followed and that 
internal code documentation standards are met . If inspections or 
some other form of peer reviews are done, the auditor should 
check that they are completed on all products and that action 
items resulting from them are carried out . 

An external audit is most effective if done early in the 
implementation phase. At this point in the life cycle, all 
control procedures are in operation and all standards are in use. 
This external SQA audit assures that they are being followed 
correctly and that status is correctly reported. If any problems 
are noted, it is early enough for meaningful change and 
corrective action. 

F . Software Integration and Test Phase 

The objectives of the integration and test phase are to integrate 
the software units into a completed system, discover and correct 
any nonconformances, and demonstrate that the system meets its 
requirements . The phase ending review is the test readiness 
review, during which the developer provides to the acquirer 
evidence that the software system is ready for acceptance 
testing. During this phase, the test plan is executed, the 
documentation is updated and completed, and the products are 
finalized for delivery. 

During this phase, internal audits include any and all of the 
items in previous phases. However, internal audits should 
concentrate on assuring that product changes made to correct 
nonconformances discovered during the testing are controlled, 
completed, and documented. Audits of the CM and NRCA processes, 
and computer program library are highly important . The SQA audit 
should include a check of the formal test procedures and the test 
results . Integration and test is often the most confusing and 
time-pressured part of a project, and there is a tendency to 
discard standards and procedures due to this pressure. 

External audits during this phase should concentrate on the same 
items as internal audits, with additional emphasis on assuring 
completeness; that is, that testing has not been shortchanged in 
order to meet schedules . 

G. Software Acceptance and Delivery Phase 

During the acceptance and delivery phase, the formal acceptance 
procedure is carried out. As a minimum, there is a requirements- 
driven demonstration of the software to show that it meets those 
requirements. The process also may include acquirer tests, field 
usage, or other arrangements that are intended to assure that the 
software will function correctly in its intended environment . 

This phase is very much like the end of the previous phase, with 
system tests being run, nonconf ormances noted, and corrections 
being made to the software, documentation, and data bases. The 
items to be audited are similar, especially the CM and NRCA 
processes . 



H. Software Sustaining Engineering and Operations Phase 

During this phase of the software life cycle, the software is 
used to achieve the objectives for which it was acquired. 
Corrections and modifications are made to the software to sustain 
its operational capabilities and to upgrade its capacity to 
support its users. Software changes may range in scope from 
simple corrective action up to major modifications that require a 
full life cycle process . 

Internal audits should respond to the extent and type of changes 
being made to the system. If there is only a low level of 
corrective action, then audits may be limited to the CM and NRCA 
procedures and to verifying that quality is being maintained in 
the products. If substantial modifications are being made, 
however, then a full or mini-life cycle should be in place and 
audits should be performed as described for the appropriate 
stage . 

When long term sustaining engineering is being performed, an 
external audit should be done periodically to assure the acquirer 
that product quality is maintained and sustained. A minimum of 
one external audit per year is recommended; more if the level of 
change activity is high. 

VI. PREPARING A CHECKLIST 

An audit checklist is a list of items that the auditor intends to 
examine and questions the auditor intends to ask during the site 
visit portion of the audit . While a generic checklist may be 
used as a basis for all audits, better results will be achieved 
if the generic checklist is tailored for each audit . Tailoring 
consists of choosing appropriate items or questions from the 
generic checklist, expanding the level of detail, adding 
additional questions and topics, and changing the wording of the 
questions to fit the project's nomenclature. Information for 
tailoring may come from the contract requirements, organizational 
standards and practices, and results and action items from 
previous audits . Additional information to be considered for 
tailoring should include the structure of the development 
organization and project, life cycle phase, and audit focus. 

In developing the checklist, the auditor should be careful not to 
overlook important information that appears to be obvious . For 
example, assuming the project has a product specification may be 
erroneous; adding that item to the checklist will help to assure 
that the information is confirmed. 

A sample generic checklist, divided by topic, is provided in 
Appendix B. Under each topic is a series of typical questions 
that should be addressed if that topic is going to be part of the 
audit. To tailor this checklist, the auditor should determine 
which topics apply to the audit and whether questions should be 
answered by interviews, examination of the software products and 
documents, examination of records, or a combination of methods. 
The auditor then should sort the questions by the method that is 
intended to be used to answer them, and further, by the precise 
source to be used. For example, questions about how CM operates 



might be asked of the CM manager during an interview, but some of 
those same questions might be directed at the person who operates 
the project's computer program library. Answers to other CM 
questions might be found through an examination of the records of 
the CM process; still others by an examination of code and 
documentation products . 

As much as possible, questions should be phrased in terms of the 
specific project and organization being audited, and should use 
the names and terms that the project uses. This tailoring will 
take some work on the part of the auditor, but this effort will 
be repaid by the fact that effective communication will be 
established earlier. 

The parts of the tailored checklist that will be answered by an 
examination of records or products should be put on a form for 
use on-site. The form can be simple, but should allow space for 
answers to each question and additional comments. The form 
should, if possible, allow the checking of boxes or simple entry 
of information. 

As the auditor proceeds with the site visit, the checklists and 
forms can be completed with the information obtained. The 
auditor must retain the flexibility to modify the forms or 
questions as information is gathered. Additional questions are 
likely to be suggested by answers given, and forms may not have 
been properly made in advance to record the real situation. It 
is important to remember that the checklist and forms derived 
from it are guides, and that the objective of the audit is to 
understand and report on the actual state of affairs in the 
developing organization. 

VII. AUDITING IN THE ABSENCE OF STANDARDS AND PROCEDURES 

An auditor may be asked to "audit" a project that lacks 
documented standards and procedures, perhaps because of warning 
signs indicated in Chapter IV. Most often, this type of audit 
will be external to the project, even if the auditor is employed 
by the developing organization, because a developer that does not 
have documented standards and procedures is unlikely to have an 
internal audit program. 

All projects generate code and documentation, but if there are no 
written standards, the products will be in the style of the 
individual technical performers or their managers. All projects 
handle changes and problems, and test their software. The 
methods may be somewhat ad-hoc and dependent on the specific 
individuals involved in a specific case, but they do exist, 
documented or not . The role of the auditor is to discover and 
document the "standards" and "procedures" that are actually 
followed . 

After the auditor has determined from interviews what "standards" 
and "procedures" are followed, the rest of the audit can proceed 
like any other audit. That is, the auditor can follow the 
progress of control paths and determine the extent to which the 
procedures are followed versus the number of exceptions that are 
allowed. The auditor can sample the products and rate their 



conformance to the (unwritten) standards. 


The auditor must gather enough information to evaluate the 
suitability and consistency of the unwritten standards and 
procedures . The auditor may be experienced enough to do the 
evaluation, or the auditor may wish to leave the evaluation to 
the management to which he/she will report. In either case, the 
auditor has to gather information on product quality, consistency 
of application of the unwritten rules, the adequacy of testing 
and reviews, and instances of confusion and/or error that may 
have resulted from uncertainty. This information is then used 
for evaluation. 

VIII. QUALITIES OF AN AUDITOR 

The major contribution of an internal or external auditor to 
project success is the collection and presentation of information 
that allows project management a clear view of the product's 
actual status and the actual compliance with standards and 
procedures. This requires an impartial auditor. In particular, 
an internal auditor must remember that covering up problems, due 
to feelings of empathy with the project staff or a desire to 
present the developer's organization in a good light, is 
counterproductive. Problems that are not brought to light will 
not be solved, and may result in much larger problems later in 
the life cycle . 

A good auditor should have a basic understanding of the software 
development life cycle and the products and processes involved in 
each of its phases . If an auditor is expected to evaluate the 
standards and procedures used by the developer and to judge their 
impact on product quality and project schedule, then he/she needs 
significant experience and background in software development and 
software management . It helps if the auditor is knowledgeable 
about the type of software being audited, and is aware of the 
specific software development procedures used in the project. It 
is useful if the auditor is experienced or trained in auditing 
techniques . 

IX. TECHNIQUES AND TOOLS 

The most frequently used tool for an SQA audit is an audit 
checklist . The checklist must be tailored to the project to be 
audited, as it provides a list of questions that must be answered 
about that particular project. 

Automated tools, either brought by the auditor or provided by the 
project, may be used if compatible with the project's standards 
and procedures. For example, the project may have a standards 
checker for code. The auditor can run the checker on a sample of 
the code, or can verify that the project runs the checker. 

The checklist tailoring and form-making process also may be 
assisted by keeping a generic checklist in a database or word 
processor. The tailored information may then be automatically 
transferred to a form or brought to the audit on a laptop 
computer . 



APPENDIX A: SQA AUDIT REPORT 


The following is the minimum content for an SQA audit report . 

1 . Background 

a. Identity of audit 

b . Date of audit 

c. Audit team members 

d. Current phase of development 

2 . Findings 

a. Version of products audited 

b. Anomalous conditions encountered 

c. Recommendation for each anomalous condition (if 
applicable) 

3 . Summary 

a. Summary of findings 

b. Status 

c. Date of follow-up or next scheduled audit 


APPENDIX B: SQA AUDIT CHECKLIST QUESTIONS 

The following is a sample master list of questions that can be 
tailored for an SQA audit . Questions appropriate to a specific 
audit should be selected and then modified to reflect local 
terminology or procedures . The questions should be placed on a 
form that allows space for recording answers . 

Questions shown in italics are mainly for use in the staff 
interviews . 

Software Assurance 

Has an SQA plan been prepared? Is it maintained current with 
program requirements? 

Has the SQA plan been submitted for approval? 

Does the SQA plan include or define: 

• SQA requirements and activities to be implemented? 

• Schedule showing when each of the activities will be 
implemented? 

• Budget for activities? 

• Specific organizational assignments? 

• Interaction between SQA and the overall development effort? 

• SQA participation in the overall change management process? 

• SQA participation in the overall test process? 

Is there evidence that SQA planned activities are implemented 
throughout the life cycle? 

Development Documentation 

Are standards for preparation of deliverable documentation 
established? 

Does the documentation meet the standards? 

Are procedures established and documented to assure that 
standards are followed? 



Do the procedures address the changes to software documentation 
that are placed under configuration management control? Are the 
changes reviewed in the same manner as the base document? 

Are methods established for traceability of documentation, 
including changes? 

Are the contents of deliverable documents clear, concise, 
complete, and understandable? 

Are procedures established to enforce consistency in writing? 

Are review teams familiar with the material being reviewed to 
detect inconsistency? 

Is approval authority for deliverable documentation clearly 
stated? 

Is required documentation provided to the acquirer in a timely, 
responsive manner? 

Are sufficient copies furnished? 

Are established procedures followed in the production of both 
deliverable and nondeliverable documents? 

Does the documentation in the development folder match the phase 
of the life cycle? 

Does the level of detail in documentation look reasonable? 

Code 

Do code, prolog, and Program Design Language (PDL) adhere to all 
prevailing standards and conventions? 

Are necessary elements of the prolog complete/ e.g., are all data 
elements described, all subroutines defined? 

Is internal code documentation present in amounts required by 
standards? 

Is the code consistent with its design, as presented in its 
prolog and PDL? 

Does the code appear to be correct for test cases that can be 
verified by a quick, visual inspection? 

Is all debug code clearly identified? 

Are all stubs and test files identified? 

Do test cases appear adequate based on the PDL? 

Configuration Management 

Has a software configuration management (CM) plan been developed? 
Has the plan been baselined? Provided to the acquirer? 

Are CM instructions for identification of baseline items and 
subsequent revision or versions being followed? 

Are CM procedures in place which require approval authority for 
adding and removing items in the program library? 

Is the CM organization adequately staffed, fully funded, and 
responsive? Are responsibilities clearly understood? 

Do baseline documents comply with contract requirements? 

Do the approved specifications serve as a baseline for control of 
changes? 

Is a list of approved specifications maintained? Current? 

Changes posted? 

Are procedures established for the production of software 
documentation adequate and rigidly enforced? 

Are procedures for handling problem reports adequate and 
efficient? 

Has a Configuration Control Board (CCB) been established? Who 



are the members? Is SQA represented? Do all members attend 
regularly? Are CCB actions handled in a timely manner? Are 
agenda and minutes published? Are CCB action items followed up? 
Are CM status accounting documents maintained? Are they current? 
Does the CM plan address configuration audits? 

Have formal configuration audits been conducted or planned 
(including FCA and PCA) ? 

Computer Program Library 

Has a Computer Program Library been established? A program 
librarian appointed? 

Have adequate procedures been identified for: Library controls? 
Configuration item controls? Problem report handling? 

Is the program librarian complying with established procedures? 
Are problem reports implemented into appropriate development 
folders? 

Are computer program versions accurately identified, controlled, 
and documented through the life cycle? Is an automated source 
control system used? Is it adequately maintained? 

How is the library controlled (error report, change request, 
etc . ) ? 

Are only authorized/approved modifications made to source and 
object programs released to the library? How is it controlled 
(error report, change request, etc.)? 

What measures are being taken to assure all approved 
modifications are properly integrated and that software submitted 
for testing is the correct version? 

Is nondeliverable software monitored and controlled to the extent 
specified in the development plan? 

Are development folders regularly submitted to the program 
librarian? 

Does a library documentation index exist? Is it current? 

Does a log exist showing what material has been checked in and 
out of the library? Does it appear accurate? 

Does all submitted code include proper transmittal information? 

Is this available for review? 

Is documentation updated to correspond with newly submitted code? 
Are all items placed in the program library assigned an 
identification number related to the version number? Does this 
number relate to the associated documentation? 

Is the flow through a change cycle clear, efficient, documented, 
and correct? (Test several samples.) 

Nonconformance Reporting and Corrective Action 

Have procedures assuring prompt detection and correction of 
deficiencies been established? 

Are data analyzed and problem and deficiency reports examined to 
determine extent and causes? 

Are trends in performance of work analyzed to prevent development 
of nonconforming products? 

Has corrective action been documented accurately on problem 
reports? 

Has corrective action been reviewed and monitored to determine 
adequacy, effectiveness, and whether contract requirements are 
being met? 



Are all corrective action reports and analyses on file? 

Is there management support for the corrective action system? 

Is the program librarian following procedures for maintaining 
control and status of problem reports? 

Are discrepancies generated by nondeliverable computer programs 
treated the same as those for deliverables? 

Are problem reports pertaining to a unit contained within the 
development folder for that unit? 

Are the software developers complying with the requirement to 
generate problem reports during integration? 

Is there documented approval for all changes to items under 
configuration control? Do all forms have required signatures? 

Verification and Validation 

Have the software requirements been analyzed to determine 
testability? 

Are test objectives adequate, feasible, and sufficient to 
demonstrate software performance to meet contractual 
requirements? Are they understood by project personnel? 

Are the test philosophy and methodology based on assumptions that 
are acceptable to SQA? Is there a procedure to monitor 
assumptions and a way to alert the test director if an assumption 
is unacceptable? 

Do test plans and procedures comply with specified standards and 
contractual requirements? 

Are the test plans and procedures approved by the acquirer, where 
required? 

Are all test tools and equipment identified, defined, calibrated, 
and controlled prior to testing the software? Is all necessary 
test hardware certified (both computer and ancillary) ? 

Is software baselined prior to testing? 

Are the correct version of software and associated documentation 
certified prior to testing? 

Are acceptance tests monitored by an SQA representative? By the 
acquirer, when required? If not, then who monitored the tests? 
Are tests conducted according to test plans and procedures? 

Have test results been certified by participating members to 
reflect the actual test findings? 

Have test reports been reviewed and certified? By whom? Are 
deficiencies documented in problem reports? 

Has test-related documentation been maintained and controlled to 
allow repeatability of tests? 

Is there a test verification matrix to assure all requirements 
are tested? Does it look reasonable? 

Are test procedures clear and repeatable? 

Do actual and expected test results match? If not, has a problem 
report been filed? 

Project Status 

Do completion dates in development folders/status sheets agree 
with status report to management? If not, how great is the 
difference? 

According to the development/management plan, the project where 
it should be? What activities should be current? How should the 
project be staffed? What intermediate projects should be 



delivered? What reviews or milestones should have occurred? 
Where does the project actually stand now? Determine: 

• Current phase 

• Activities levels 

• Staff composition 

• Documents delivered 

• Milestones reached 

• Results of reviews .